Hi
I am constructing two floors of house in a 30*40 plot in Bangalore. I have got plan approval from BBMP and started construction. I want to know after completion of construction do I need anything else from BBMP? I have read about occupancy certificate for apartments which have more than five units but since mine is a single unit is there anything else that I need to get done after construction?
Thanks
Krishna
Query on BBMP certificate after construction completion
-
- Posts: 83
- Joined: April 25th, 2011, 4:11 pm
- ecopackindia
- Posts: 46
- Joined: May 4th, 2010, 3:44 pm
Re: Query on BBMP certificate after construction completion
Dear Sir,
Occupancy Certificate is not required/issued for G+1 residential building constructed in 30feetX40feet, but construct as per the sanctioned plan to avoid issues. 5% of Deviation is permitted with penalty.
EP Team
Occupancy Certificate is not required/issued for G+1 residential building constructed in 30feetX40feet, but construct as per the sanctioned plan to avoid issues. 5% of Deviation is permitted with penalty.
EP Team
Re: Query on BBMP certificate after construction completion
Hi,
This thread is very useful.
I Am constructing a G+ FF + SF(Duplex) so ideally G+3levels(30x40 site) on a B-khata there is no plan for this, as we all know, BBMP gives no plan.
So in this case, what is the work around, can anyone share your exp.
Thanks
Avi
This thread is very useful.
I Am constructing a G+ FF + SF(Duplex) so ideally G+3levels(30x40 site) on a B-khata there is no plan for this, as we all know, BBMP gives no plan.
So in this case, what is the work around, can anyone share your exp.
Thanks