order of work in construction

chandraklc
Posts: 72
Joined: December 7th, 2011, 11:50 am

order of work in construction

Post by chandraklc »

Hi,

we are in the midlle of construction of duplex house. wall construction and inside platering is done now. outside plastering is pending. can you please let me know what are the order of work from now onwards, granite laying person is saying one coat wall putty shud be done before granite, but walls are still in curing stage i am not sure whether wall putty at this stage is correct.
our pending work is
plumbing in all batch room
painting
granite laying in common area and vitrified tiles in all rooms
interiors like wardrobes and kitchen work.

please let me know the order of execution for better life of each components.

thanks
chandra
sunilbg08
Posts: 4
Joined: November 10th, 2020, 7:54 pm

Re: order of work in construction

Post by sunilbg08 »

Hey.
I am listed few jobs
1) first complete curing for plastering.
2) you can also complete plumbing inside line work.
3) after curing, go for wall putty coats
4)then start granite laying work.
4.1) outside plastering
5) painting of primer and one coat paint.
6) electrical wiring inside
7) you can start Interior wood work
8) outside plumbing work.
9) compound wall and grill work.

Regards
Sunil Gollagi
sunilgollagi@gmail.com
sunilbg08
Posts: 4
Joined: November 10th, 2020, 7:54 pm

Re: order of work in construction

Post by sunilbg08 »

Hey.
I am listed few jobs
1) first complete curing for plastering.
2) you can also complete plumbing inside line work.
3) after curing, go for wall putty coats
4)then start granite laying work.
4.1) outside plastering
5) painting of primer and one coat paint.
6) electrical wiring inside
7) you can start Interior wood work
8) outside plumbing work.
9) compound wall and grill work.

Regards
Sunil Gollagi
sunilgollagi@gmail.com
chandraklc
Posts: 72
Joined: December 7th, 2011, 11:50 am

Re: order of work in construction

Post by chandraklc »

Hi sunil,

thanks for the valuable input. is there any prob if i go for granite first then wall putty? holding these people in a line is really challenging. electric wire of pipe laying shud be done before plastering right.

thanks
chandra
RashmiL
Posts: 169
Joined: January 22nd, 2021, 9:19 am

Re: order of work in construction

Post by RashmiL »

It's off topic , but important. Always do wiring when you have doors installed. I had heard few cases of wire theft.
sunilbg08
Posts: 4
Joined: November 10th, 2020, 7:54 pm

Re: order of work in construction

Post by sunilbg08 »

No. there is no problem. But there is chance of scratch on granite.becuase painter will drag stools and bucket etc on floor.
chandraklc
Posts: 72
Joined: December 7th, 2011, 11:50 am

Re: order of work in construction

Post by chandraklc »

RashmiL wrote:
June 17th, 2021, 9:23 pm
It's off topic , but important. Always do wiring when you have doors installed. I had heard few cases of wire theft.
in our case it should not be a problem, we are living in ground floor already from few years and constructing duplex now from first floor. thanks for suggestion
Visualizer
Posts: 375
Joined: June 1st, 2018, 6:24 pm

Re: order of work in construction

Post by Visualizer »

Put a layer of POP on floor after granite or tiles are laid this POP will be removed only before you move in and will protect your floor from drops of hammer scratches etc.
Will cost some 10-20K depending on floor area but totally worth.

Sequence as per me
1. Rough plaster of bathroom walls
2. Electrical and plumbing groove cutting can continue in parallel.
If you want to hire inetrior designer for complete project engage at this point as lighting and furniture arrangement is also done by them else continue as per your plan.

3. Bathroom concealed fittings purchase and fitting divertor/mixer/thermostat etc.

4. Plaster repair for grooves cut , bathroom floor and lower portion of wall waterproofing , bathroom tiling.
Choosing and buying bathroom tiles is very laborious and time consuming.

5. putty and false ceiling (if any)

6. Granite actually point 5 putty can continue in parallel

7. Exterior primer coat can continue in parallel with granite and interior putty.

8. Door frame fitting

9. Plaster repair for door frames and crack filling.

10. Granite strips for door jamb and window cills
11. Window frames /UPVC
12. Wiring switching MCB rCCB fuse etc
13. Meter box and underground cable.
14. Window grill and MS steel painting.
15. Interior paint 1 coat and exterior paint
16..Main door fixing
17. Interior work and wardrobes + modular kitchen
18. Sumptank and oveehead tank cleaning, checking of sanitary lines and chamber.
19. Lids on sewage chambers and underground sump covers.
20. Electrcal fittings fans, exhaust, lights , geysers
21. Final coat of interior paint.
22 Drive all other workers out
23. Fixing bathroom fittings CP parts and sanitory ware.
24. Fix concealed lock on main door
25. Udghatan/puja/housewarming
Last edited by Visualizer on June 25th, 2021, 7:36 pm, edited 1 time in total.
chandraklc
Posts: 72
Joined: December 7th, 2011, 11:50 am

Re: order of work in construction

Post by chandraklc »

Visualizer wrote:
June 23rd, 2021, 12:49 am
Put a layer of POP on floor aftee granite and tiles are laid this POP will be removed only before you move in and will protect your floor from drops of hammer scratches etc.
Wi coat some 10-20K depending on floor area but totally worth.

Sequence as per me
1. Rough plaster of bathroom walls
2. Electrical and plumbing groove cutting can continue in parallel.
If you want to hire inetrior designer for complete project engage at this point as lighting and furniture arrangement is also done by them else continue as per your plan.

3. Bathroom concealed fittings purchase and fitting divertor/mixer/thermostat etc.

4. Plaster repair for grooves cut , bathroom floor and lower portion of wall waterproofing , bathroom tiling.
Choosing and buying bathroom tiles is very laborious and time consuming.

5. putty and false ceiling (if any)

6. Granite actually point 5 putty can continue in parallel

7. Exterior primer coat can continue in parallel with granite and interior putty.

8. Door frame fitting

9. Plaster repair for door frames and crack filling.

10. Granite strips for door jamb and window cills
11. Window frames /UPVC
12. Wiring switching MCB rCCB fuse etc
13. Meter box and underground cable.
14. Window grill and MS steel painting.
15. Interior paint 1 coat and exterior paint
16..Main door fixing
17. Interior work and wardrobes + modular kitchen
18. Sumptank and oveehead tank cleaning, checking of sanitary lines and chamber.
19. Lids on sewage chambers and underground sump covers.
20. Electrcal fittings fans, exhaust, lights , geysers
21. Final coat of interior paint.
22 Drive all other workers out
23. Fixing bathroom fittings CP parts and sanitory ware.
24. Fix concealed lock on main door
25. Udghatan/puja/housewarming
Hi Visualizer,

that was very detailed explanation. thanks for the inputs.
saran88
Posts: 38
Joined: July 25th, 2020, 10:08 pm

Re: order of work in construction

Post by saran88 »

Thanku Sunil and Visualizer. It's useful.