Currently we had planned three pipes. one inlet from water source. One 6'' pipe towards the gate for tanker if required in future and one pipe to fill the overhead tank.. But i will have one for overflow.
Completed the sump plastering after laying the chicken mesh & iron rod..
Pillars till the Plinth level has been layed. Earth will be filled back and planning to leave Two tankers for water over the weekend for the refill to settle down.
Plinth beam will be fixed early next week..
Had a vistor come near the site. He claims there is a case against the sites in the particular survey number in Anekal court and his suggestion was to go for a settlement by approaching their lawyer.. I have humbly told him not to waste his time and bring a stay order if he wants me to stop the work.
Looks like all sites in Bangalore have a litigation case