Hi all,
Two labor contractors have quoted Rs.26K per chadra. The exclusions are,
Earth work,
Parapet wall
Roof surki/Muddi,
Footings,
Watch man room,
Curing above 4 times a day,
Curing for moulding during curing period,
Demolitions and re-work,
Sump,
Chain Staircase (Half charge)
Elevaion works,
Corner designs on ceiling,
Watch man salary.
He says the measurement is roof area.
Is Rs.26K on the higher side. Is there any more points to be clarified with the Labour contractor ? Will there be dark areas which he would take advantage while payment is made. Since I have no idea about the step by step civil works involved , I could not catagorically ask him about all the inclusions.
Regarding payment, he says the payments are to be made weekly. How to calculate the quantum of work executed ? Wouldn't at some point of time the actual payment made will over shoot the quantity of work done at which time the contractor will loose interest in continuing the work ?
Your valuable inputs are requested.