Construction Stages
Posted: January 9th, 2012, 1:21 pm
Hi,
I could not find a thread on construction process explained in detail. I am constructing my house and would require advise on things that needs to be taken care during construction. Since I need to double check what my engineer or contractor is saying is correct, i need some technical knowledge about the construction process. The details i need is the steps that need to be followed from earth work till the finishing of the house.
1) Foundation : grade of cement, concrete mixing ratio, curing time required for the column structure
2) construction of walls and lintel - concrete mixing ratio, curing time required before strating the lintel
3) Beams: concrete mixing ratio, curing time required etc
4) Roof slab - Concrete mixing ratio, grade of cement. curing time etc. Many say cruing is not required for the roof slab for 21 days and load can be put on the roof very next day after the completion and the next floor can be raised. Please clarify this as to how many days the construction has to stop for curing purpose and how many days any load should not be applied on the roof.
5) Electrical work - at what stage of the construction should this start and details to be taken care.
6) Carpenter - at what stage of the construction should this start and details to be taken care.
7) Grill work for windows etc. - at what stage of the construction should this start and details to be taken care.
8) Plumbing - at what stage of the construction should this start and details to be taken care.
There would be many other stages of the construction that i need to take care. Request you to explain the complete construction stages for my reference so that I can be able to understand things and double check with what the contractor says..
Thanks
Yogi
I could not find a thread on construction process explained in detail. I am constructing my house and would require advise on things that needs to be taken care during construction. Since I need to double check what my engineer or contractor is saying is correct, i need some technical knowledge about the construction process. The details i need is the steps that need to be followed from earth work till the finishing of the house.
1) Foundation : grade of cement, concrete mixing ratio, curing time required for the column structure
2) construction of walls and lintel - concrete mixing ratio, curing time required before strating the lintel
3) Beams: concrete mixing ratio, curing time required etc
4) Roof slab - Concrete mixing ratio, grade of cement. curing time etc. Many say cruing is not required for the roof slab for 21 days and load can be put on the roof very next day after the completion and the next floor can be raised. Please clarify this as to how many days the construction has to stop for curing purpose and how many days any load should not be applied on the roof.
5) Electrical work - at what stage of the construction should this start and details to be taken care.
6) Carpenter - at what stage of the construction should this start and details to be taken care.
7) Grill work for windows etc. - at what stage of the construction should this start and details to be taken care.
8) Plumbing - at what stage of the construction should this start and details to be taken care.
There would be many other stages of the construction that i need to take care. Request you to explain the complete construction stages for my reference so that I can be able to understand things and double check with what the contractor says..
Thanks
Yogi