Can any body have Idea about the cost of following items on a material+installation basis, contractor will purchase, and install
all the items. (reinforcement bending and centering will be extra at the rate of Rs. 62500/Ton)
All concrete work in M200 (1:1.5:3)
Plinth Beams : Rs. 230 / CFT
Columns : Rs. 205 / CFT (Gr. Floor), Rs. 205 / CFT (1st Floor), Rs. 205 / CFT (2nd Floor), Rs. 245 / CFT (3rd Floor), Rs. 260 / CFT (Terrace Floor).
Lintel : Rs. 245 / CFT (Gr. Floor), Rs. 250 / CFT (1st Floor), Rs. 255 / CFT (2nd Floor), Rs. 275 / CFT (3rd Floor).
Roof Beam : Rs. 245 / CFT (Gr. Floor), Rs. 250 / CFT (1st Floor), Rs. 255 / CFT (2nd Floor), Rs. 295 / CFT (3rd Floor), Rs. 310 / CFT (Terrace Floor).
Chajja : Rs. 85 / SFT (Gr. Floor), Rs. 90 / SFT (1st Floor), Rs. 95 / SFT (2nd Floor), Rs. 100 / SFT (3rd Floor).
Roof Slab : Rs. 245 / CFT (Gr. Floor), Rs. 250 / CFT (1st Floor), Rs. 255 / CFT (2nd Floor), Rs. 285 / CFT (3rd Floor), Rs. 300 / CFT (Terrace Floor).
Staircase : Rs. 260 / CFT (Gr. Floor), Rs. 265 / CFT (1st Floor), Rs. 270 / CFT (2nd Floor), Rs. 275 / CFT (3rd Floor).
8" thk Solid Block Wall : Rs. 115 / SFT (Gr. Floor), Rs. 120 / SFT (1st Floor), Rs. 125 / SFT (2nd Floor), Rs. 148 / SFT (3rd Floor), Rs. 160 / SFT (Terrace Floor).
6" thk Solid Block Wall : Rs. 95 / SFT (Gr. Floor), Rs. 100 / SFT (1st Floor), Rs. 105 / SFT (2nd Floor), Rs. 130 / SFT (3rd Floor), Rs. 140 / SFT (Terrace Floor).
4" thk Solid Block Wall : Rs. 85 / SFT (Gr. Floor), Rs. 90 / SFT (1st Floor), Rs. 95 / SFT (2nd Floor), Rs. 110 / SFT (3rd Floor), Rs. 120 / SFT (Terrace Floor).
soon replies will be highly appreciated.
regards.
Quotes for Civil and Concrete Work (Material+Installation)
Re: Quotes for Civil and Concrete Work (Material+Installatio
I think the rates for concrete are on lower side. Even my project that started last year had higher initial quote and I had to revise it due to recent increase in cement/sand prices. Not sure if one can buy good quality sand+cement+20mm in this price.
Please cross check with my contractor too. Sent you PM with details.
Please cross check with my contractor too. Sent you PM with details.
Re: Quotes for Civil and Concrete Work (Material+Installatio
Dear Girish,
this prices doesn't include reinforcement and centering, those expenses are extra at Rs. 62500/ton,
I called your contractor but he was not able to speak of language barrier, can you please share your
prices of the listed above so that others will also get an idea about those item prices. please.
this prices doesn't include reinforcement and centering, those expenses are extra at Rs. 62500/ton,
I called your contractor but he was not able to speak of language barrier, can you please share your
prices of the listed above so that others will also get an idea about those item prices. please.