Page 2 of 2
Re: House Construction in Mysore
Posted: July 16th, 2015, 6:41 am
by ausraja
satish in which locality of mysore is this house located ? interested as myself from mysore.For what cost have you agreed this construction in mysore ?
Re: House Construction in Mysore
Posted: July 16th, 2015, 11:08 am
by hcsatish
Hi ausraja,
The place is near Nivedita Nagar, Bogadi 2nd stage, just before ring road. We have agreed for item wise rate contract. Project cost is estimated around 40lacs.
Will share the Item rate quote shortly.
Re: House Construction in Mysore
Posted: July 19th, 2015, 5:00 pm
by hcsatish

- Basic Rate quoted by Contractor
- Basic Rate.jpg (86.38 KiB) Viewed 9659 times
Regards,
Satish
Re: House Construction in Mysore
Posted: July 20th, 2015, 1:23 pm
by hcsatish

- IMG_0832.JPG (134.86 KiB) Viewed 9628 times

- IMG_0832.JPG (134.86 KiB) Viewed 9628 times
Wall construction completed till lintel level. 3 days off to make sure proper curing of walls before starting centering and lintel level beam work.
Some of the wall construction pictures are attached.
Re: House Construction in Mysore
Posted: August 4th, 2015, 9:10 am
by shri
Hi Satish,
Congrats!.
Can you share some details on how much he is charging per sq/ft. Could you also share the details of the contractor and the architect?
How much do we need to pay for the architect? Also, are you planning to hire someone to keep tabs on the construction. I am asking that
because i don't live in bangalore and can come over during the weekend for a day or so. Is the presence of the owner needed all the time
to ensure good quality construction?
Re: House Construction in Mysore
Posted: August 24th, 2016, 2:54 pm
by hcsatish
Completed House construction !!!! Did Griha Pravesh on 21st
It took almost 14months to complete the work. Would like to thank this forum and forum member for knowledge base.

- Screen Shot 2016-08-24 at 2.51.00 PM.png (714.87 KiB) Viewed 9307 times

- Screen Shot 2016-08-24 at 2.51.17 PM.png (524.71 KiB) Viewed 9307 times
Re: House Construction in Mysore
Posted: August 26th, 2016, 2:53 pm
by ramki067
hcsatish wrote:Completed House construction !!!! Did Griha Pravesh on 21st
It took almost 14months to complete the work. Would like to thank this forum and forum member for knowledge base.Screen Shot 2016-08-24 at 2.51.00 PM.pngScreen Shot 2016-08-24 at 2.51.17 PM.png
@hcsatish, Your home has come out very well. Wishing you a very happy livelihood in your new home from long years to come

Between can you give me the address of the Bidadi factory from where you purchased M Sand?
Thanks,
Ramki
Re: House Construction in Mysore
Posted: January 21st, 2017, 9:18 pm
by shri
HI satish,
Your house has come up very beautifully. Whats the going rate at Mysore per sq/ft. Any idea?
Also, Can you share your architect and contractor details thorough message.
Thanks for your time.