Finally Started my construction a Duplex 30X50 site in EC...

m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

Yesterday had been to Bangalore Tiles near Kudlu, This shop was referred by the contractor as it was the bigger shop around our place.

we had selected few designs from Khajaria before we went there, Unfortunately the prices were quite high for our choices around RS 135/sqft the basic model was Rs 60/sqft. I am planning to check for Granite also in parallel.

The plastering minus elevation should get over by this week..
Regards,
Martin
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

External Staircase Railings work
Attachments
External Staircase Railings work
External Staircase Railings work
20140902_083845.jpg (265.07 KiB) Viewed 8951 times
Regards,
Martin
jawaharsettu
Posts: 13
Joined: October 7th, 2013, 11:56 am

Re: Finally Started my construction a Duplex 30X50 site in E

Post by jawaharsettu »

Hi Martin,

Your house construction coming out really well.
How much you paid for the staircase MS grill. Is the cost based on running feet or based on Kg.

Regards
Jawahar
krikks
Posts: 12
Joined: March 29th, 2014, 2:25 am

Re: Finally Started my construction a Duplex 30X50 site in E

Post by krikks »

Martin,

Quick question: Don't see chajja(sun shade) at all for the front facing window on first floor, side ground floor. I see chajja with large openings for the side-first floor windows. Are you not worried about rain water ingress through your wood framed windows? Do you plan to retrofit a glass chajja with steel frame? Would love to hear your thought process on this.
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

Thanks Jawahar, Unfortunately i don't know the exact cost as mine is a material contract, The total cost what the contractor said was around 1.15 L.

@krikks - what the contractor explained is that it will have a 6 Inches Chejja and Top near first floor roof will have glass covering. However My uncle is visiting the site in couple of weeks i am waiting to get some inputs from him.
Regards,
Martin
gsNagesh
Posts: 45
Joined: October 12th, 2010, 2:03 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by gsNagesh »

@Martin,


Glass Covering for good lighting once the adjacent building comes up, Nice idea. Looks like its through and through whole length from the picture (assuming), will it not effect the ventilation? Is there any elevation picture which shows how does it come up?

- Nagesh
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

@Nagesh.

These were not included in the Elevation, Something we created during the construction. With the Room being built on the top. matching the initial elevation has become a challenge. We are still figuring out how we need the final elevation to look like. :?:
Regards,
Martin
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

Elevation Comparison.

Today had also been to Jigani to check for Granite. Went to Solar Granite's Through reference i have kind of shortlisted couple of Granite's, Planning to complete the purchase on Saturday.
Attachments
Elevation
Elevation
Granite
Granite
Granite.jpg (397.29 KiB) Viewed 8825 times
Regards,
Martin
biddappa_c_b
Posts: 186
Joined: November 1st, 2011, 6:30 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by biddappa_c_b »

Could you please let me know the cost of granites that you have shortlisted?

thanks
m_d1982
Posts: 137
Joined: January 13th, 2012, 2:10 pm

Re: Finally Started my construction a Duplex 30X50 site in E

Post by m_d1982 »

@biddappa_c_b,
Will update you on Saturday, i have not yet discussed the cost with the Granite vendor, I am looking at something around 80 - 100 Rs range. On the contract i have rs 60/Sqft
Regards,
Martin
Post Reply