Sand quantity estimation - urgent

Post Reply
rrprakash
Posts: 54
Joined: October 16th, 2012, 8:07 am

Sand quantity estimation - urgent

Post by rrprakash »

I am planning to construct 2000 sq.ft. Duplex house with framed structure (column & beams).

Can any member share approx. quantity of sand required in CFT for this type of construction.

Any information on total loads of Sand procured with approx. CFT per load for any completed / under construction building with details of No. of floors, sq. ft. area, etc. will also do.

This is will be very much helpful for my cost estimation.

Regards
venkyn
Posts: 305
Joined: September 11th, 2010, 2:50 pm

Re: Sand quantity estimation - urgent

Post by venkyn »

for 3200sq building, we consumed below quantity. The building is red brick building so the consumotion is more.

Foundation 1/10/2014 6 wheeeler Mysore road 4 26600
Foundation 10/10/2014 6 wheeeler Mysore road 5 26000
Foundation 18/10/2014 10 wheeeler Direct Tirchy 5 36000
Lintle 18/11/2014 6 wheeeler Direct Tirchy 4 24500
GF Roof
  • [img][/img]
28/11/2014 6 wheeeler Sakaleshpur 4 24000
FF Construction 18/12/2014 10 wheeeler Direct Tirchy 5 35000
FF Roof 4/1/2015 6 wheeeler Tirchy 3.8 23000
SF Piller 15/1/2015 6 wheeeler Tirchy 3.8 23000
SF Lintle and Roof 10/2/2015 6 Wheeler Sakaleshpur 4 25300
SF Lintle and Roof 10/2/2015 6 Wheeler Sakaleshpur 4 25800
SF Lintle and Roof 1/3/2015 10 Wheeler HoleNarsipura 6 75000
plasting 6Wheeler Trichy 3 38000
Plasting 10Wheeler Trichy 5 58000
30/4/2015 6 Wheeler Sakaleshpur 3.8 32000
rrprakash
Posts: 54
Joined: October 16th, 2012, 8:07 am

Re: Sand quantity estimation - urgent

Post by rrprakash »

@venkyn,

Thanks for the details.

I presume, the quantity you have given is in terms of "UNITS" and the conversion will be 1 UNIT = 100 cft.

Total quantity consumed : 6040 cft for 3200 sq. ft. building, i.e. 1.9 cft/sq.ft.

Kindly confirm.

Regards
bala4034
Posts: 22
Joined: August 4th, 2013, 7:16 pm

Re: Sand quantity estimation - urgent

Post by bala4034 »

Dear Venkyn,
Can you please share the labour cost (rate/SFT) for the plastering,
Also if you finish the Painting can you please share the labour cost for the Enxternal & Internal Painting.
venkyn
Posts: 305
Joined: September 11th, 2010, 2:50 pm

Re: Sand quantity estimation - urgent

Post by venkyn »

Bala,

The labour contract is given for the entire building.. the sand quantity is for the activitiy done.

Venkyn
Simran
Posts: 68
Joined: November 5th, 2014, 3:17 pm

Re: Sand quantity estimation - urgent

Post by Simran »

My building consumed 5900 cft of sand for structure and plastering. Total built-up is around 4300 sft, cement block construction, Karur and trichy sand.
The measurement is accurate, not the measurement told by the supplier. For example before the sand strike, ie until January end, the supplier used to tell 370-380cft for 6 wheeler and 540-580cft for 10 wheeler.

We used to measure each load (different lorries) and found that the actual measurement was as following:

6 wheeler full load (before strike) : 320-330cft
10 wheeler full load (before strike) : 480-500 cft
6 wheeler body level load (post strike) : 270-280cft
10 wheeler body level load (post strike) : 400-420 cft

If we go by the sand supplier's words, then my building has consumed about 7000 cft.
bala4034
Posts: 22
Joined: August 4th, 2013, 7:16 pm

Re: Sand quantity estimation - urgent

Post by bala4034 »

Dear Simran,
good peice of information, what is the price you paid for this, where did u buy this?

thanks
Post Reply