Full Contract
Posted: November 25th, 2014, 1:01 pm
by firsttimebuilder
Hi All,
I am planning to construct basement/GF/FF. The Civil Engineer/Architect is suggesting his charges would be cost of the material + 10 %.
Can somebody suggest is it ok to agree for cost+10% agreement. Any valuable feedback is greatly appreciated.
Thanks,
Re: Full Contract
Posted: November 26th, 2014, 8:34 pm
by ashok.chava
My Contractor is quoting 1850 per Sqft for G+2(G- 2 bed room for rental and 1 and 2 are duplex). The quote does not include compound wall and vitrified tiles (cost Rs. 60). I don't know if its too much. I am also looking for a feed back.
Re: Full Contract
Posted: November 27th, 2014, 11:57 am
by nagzzz
@firsttimebuilder- depends on what all work is being quoted. For the structure (includes everything except for Interior design) is about 5-6%. this will include all drawings, elevation, floor plans, electrical and plumbing plans, stairs design, house flooring designs, paint scheme.
If the architect is also doing all interiors, then 10% is decent. this would additionally include your wardrobes, kitchen, furnishing etc.
@ashok-1850 without flooring is too much. anyway, this is not the right away of take a quote. A Basic contract can start from Rs 1300/- going all the way till 2500/- and even beyond. first take a quote and check what Cement, sand, steel, flooring, paint, plumbing, fittings, tiles etc is being given in the quote. Don't fix up the price upfront. If you want, I can give you details about the contractor who did my house. cheers.
Re: Full Contract
Posted: November 27th, 2014, 12:05 pm
by ashok.chava
Hi Nag,
Can you please provide me your contractor details?
Ashok Chava
Re: Full Contract
Posted: December 31st, 2014, 11:16 pm
by mgmprasad
Hi Nag
Can you please send me the details too to my mail id
mgmprasad@gmail.com.
Also your phone number if you dont mind.
Thanks
Prasad
Re: Full Contract
Posted: January 1st, 2015, 7:38 am
by rrprakash
Hi Nag,
I am also in look out for a good contractor who can take up job with item rate contract.
Kindly PM your contractor details.
Regards
Re: Full Contract
Posted: January 1st, 2015, 11:44 am
by girishd
mgmprasad, rrprakash,
You can speak to Gopal (7676277763). He is currently working on my project (6300 sft) which is pretty much done on structure portion and in finishing stage. I am reasonably happy with his work. If needed you can have a look at my site near Jambu Savari Dinne @J P Nagar 8th Phase. PM me for details.
Re: Full Contract
Posted: January 4th, 2015, 9:31 am
by sandeephc10
Hello Friends,
A Very good reliable Contractor Contact is known to me, i have seen his work and its really good.
You can contact this person- Subramani 9448088499
Re: Full Contract
Posted: September 8th, 2015, 7:42 pm
by girishshk
Can any one provide a reference for good labor contract, i understand that there will be atleast 10% margin for material contract.
Re: Full Contract
Posted: September 25th, 2015, 11:32 pm
by karjagir
Girish,
My contractor is pretty good and I have found him to be a very ethical person. Where is your site located ? I can check with him and provide details. He generally does not take more than 2 projects at a time due to monitoring challenges and he cannot travel very far so I will need to check with him first
Karthik