Full Contract

firsttimebuilder
Posts: 7
Joined: November 7th, 2014, 2:51 pm

Full Contract

Postby firsttimebuilder » November 25th, 2014, 1:01 pm

Hi All,
I am planning to construct basement/GF/FF. The Civil Engineer/Architect is suggesting his charges would be cost of the material + 10 %.

Can somebody suggest is it ok to agree for cost+10% agreement. Any valuable feedback is greatly appreciated.

Thanks,

ashok.chava
Posts: 21
Joined: September 24th, 2014, 10:23 am

Re: Full Contract

Postby ashok.chava » November 26th, 2014, 8:34 pm

My Contractor is quoting 1850 per Sqft for G+2(G- 2 bed room for rental and 1 and 2 are duplex). The quote does not include compound wall and vitrified tiles (cost Rs. 60). I don't know if its too much. I am also looking for a feed back.

nagzzz
Posts: 116
Joined: January 24th, 2014, 10:03 am

Re: Full Contract

Postby nagzzz » November 27th, 2014, 11:57 am

@firsttimebuilder- depends on what all work is being quoted. For the structure (includes everything except for Interior design) is about 5-6%. this will include all drawings, elevation, floor plans, electrical and plumbing plans, stairs design, house flooring designs, paint scheme.
If the architect is also doing all interiors, then 10% is decent. this would additionally include your wardrobes, kitchen, furnishing etc.

@ashok-1850 without flooring is too much. anyway, this is not the right away of take a quote. A Basic contract can start from Rs 1300/- going all the way till 2500/- and even beyond. first take a quote and check what Cement, sand, steel, flooring, paint, plumbing, fittings, tiles etc is being given in the quote. Don't fix up the price upfront. If you want, I can give you details about the contractor who did my house. cheers.

ashok.chava
Posts: 21
Joined: September 24th, 2014, 10:23 am

Re: Full Contract

Postby ashok.chava » November 27th, 2014, 12:05 pm

Hi Nag,

Can you please provide me your contractor details?

Ashok Chava

mgmprasad
Posts: 7
Joined: December 26th, 2011, 1:11 pm

Re: Full Contract

Postby mgmprasad » December 31st, 2014, 11:16 pm

Hi Nag

Can you please send me the details too to my mail id mgmprasad@gmail.com.
Also your phone number if you dont mind.

Thanks
Prasad

rrprakash
Posts: 54
Joined: October 16th, 2012, 8:07 am

Re: Full Contract

Postby rrprakash » January 1st, 2015, 7:38 am

Hi Nag,

I am also in look out for a good contractor who can take up job with item rate contract.

Kindly PM your contractor details.

Regards

girishd
Posts: 238
Joined: May 22nd, 2012, 8:29 am

Re: Full Contract

Postby girishd » January 1st, 2015, 11:44 am

mgmprasad, rrprakash,

You can speak to Gopal (7676277763). He is currently working on my project (6300 sft) which is pretty much done on structure portion and in finishing stage. I am reasonably happy with his work. If needed you can have a look at my site near Jambu Savari Dinne @J P Nagar 8th Phase. PM me for details.

sandeephc10
Posts: 7
Joined: April 16th, 2013, 5:51 pm

Re: Full Contract

Postby sandeephc10 » January 4th, 2015, 9:31 am

Hello Friends,

A Very good reliable Contractor Contact is known to me, i have seen his work and its really good.
You can contact this person- Subramani 9448088499

girishshk
Posts: 120
Joined: April 18th, 2012, 9:26 am

Re: Full Contract

Postby girishshk » September 8th, 2015, 7:42 pm

Can any one provide a reference for good labor contract, i understand that there will be atleast 10% margin for material contract.

karjagir
Posts: 25
Joined: September 18th, 2015, 5:30 pm

Re: Full Contract

Postby karjagir » September 25th, 2015, 11:32 pm

Girish,

My contractor is pretty good and I have found him to be a very ethical person. Where is your site located ? I can check with him and provide details. He generally does not take more than 2 projects at a time due to monitoring challenges and he cannot travel very far so I will need to check with him first