- October 25th, 2017, 1:24 am
- Forum: Civil Construction
- Topic: Any good electrician in Hosa road area
- Replies: 1
- Views: 3239
Re: Any good electrician in Hosa road area
You can contact. Mr Rajesh 9945439339
- April 17th, 2015, 11:46 pm
- Forum: Civil Construction
- Topic: Gauribidanur sand
- Replies: 2
- Views: 5400
Re: Gauribidanur sand
Gouribidnur sand or from anywhere should use river sand instead of filter or mixed sand , since the clients are non technical they can say some good words and impress when come to reality its totally different story,
M sand cant be used for plastering as well as block work, it can be only used for ...
M sand cant be used for plastering as well as block work, it can be only used for ...
- January 6th, 2015, 11:22 pm
- Forum: Site for sale
- Topic: 20x30 BDA site sale JP Nagar 9th phase, I Block
- Replies: 1
- Views: 4213
Re: 20x30 BDA site sale JP Nagar 9th phase, I Block
is this site still available
- October 9th, 2014, 12:07 am
- Forum: Civil Construction
- Topic: COntractor reference to construct boundary wall for a plot
- Replies: 17
- Views: 24980
Re: COntractor reference to construct boundary wall for a pl
Hi - Can you please recommend some good and reliable contactors to construct a boundary wall for a plot in north bangalore?
hi,
i suggest to you to freeze basic requirement items and activities.
Material -- 1.solid block 8" or 6" ( 4" not advisable since it may not be strong)
2. precast ...
hi,
i suggest to you to freeze basic requirement items and activities.
Material -- 1.solid block 8" or 6" ( 4" not advisable since it may not be strong)
2. precast ...
- June 27th, 2014, 1:07 pm
- Forum: Civil Construction
- Topic: Cnstructn on 30x40 plot(Ground Floor) Need advice on estmtn.
- Replies: 8
- Views: 8982
Re: Cnstructn on 30x40 plot(Ground Floor) Need advice on est
hi shivashashi
I agree with Mr. praveen
if plan , elevations , structural details are ready or freeze the requirement first . once details are ready
my suggestion is please ask him to provide the quote with quantity and rate for all works including basic cost of materials and make or brand of ...
I agree with Mr. praveen
if plan , elevations , structural details are ready or freeze the requirement first . once details are ready
my suggestion is please ask him to provide the quote with quantity and rate for all works including basic cost of materials and make or brand of ...
- November 18th, 2013, 2:10 am
- Forum: Material prices
- Topic: Ground floor roof slab.
- Replies: 4
- Views: 5083
Re: Ground floor roof slab.
hi all
side shuttering can be removed after 24 hours. but slab shuttering removal depends on the length of of slab if the slab length is more than 4.5 mtr with out any beam, slab shuttering should be removed after 14 days if less than 14 mtr shuttering can be removed after 7 days by providing jack ...
side shuttering can be removed after 24 hours. but slab shuttering removal depends on the length of of slab if the slab length is more than 4.5 mtr with out any beam, slab shuttering should be removed after 14 days if less than 14 mtr shuttering can be removed after 7 days by providing jack ...
- November 15th, 2013, 11:52 pm
- Forum: Civil Construction
- Topic: Review my Building Spec/Quote @1400 for basic Construction
- Replies: 6
- Views: 8658
Re: Review my Building Spec/Quote @1400 for basic Constructi
hi pals 78
MS staircase for overhead tank will be part of contract, if the RCC staircase is outside of slab area then the it should be considered as 1 square or 100 sft in your case it will be inside of building.
why i said 12000 means 1 tanker load contains 6000 ltrs, so when you want to water ...
MS staircase for overhead tank will be part of contract, if the RCC staircase is outside of slab area then the it should be considered as 1 square or 100 sft in your case it will be inside of building.
why i said 12000 means 1 tanker load contains 6000 ltrs, so when you want to water ...
- November 15th, 2013, 5:17 am
- Forum: Civil Construction
- Topic: Review my Building Spec/Quote @1400 for basic Construction
- Replies: 6
- Views: 8658
Re: Review my Building Spec/Quote @1400 for basic Constructi
hi pals78
we should be really thankful to My BDA site ADMIN guys for proving opportunity to share knowledge,
I reviewed your quote and specification with plan .
I am sharing my knowledge for my best
This may really help all other readers too
the price you got per square is very good and best ...
we should be really thankful to My BDA site ADMIN guys for proving opportunity to share knowledge,
I reviewed your quote and specification with plan .
I am sharing my knowledge for my best
This may really help all other readers too
the price you got per square is very good and best ...
- November 15th, 2013, 2:17 am
- Forum: Civil Construction
- Topic: construction methods for bathrooms in FF and SF.
- Replies: 4
- Views: 24779
Re: construction methods for bathrooms in FF and SF.
hi,
as Mr aries said the toilet level should be at least 12mm down by floor level of bedroom or hall it should not be above bedroom level proper sunked to be provided on slab itself while designing the slab , sunken should be treated by waterproof course up to 1 feet above the floor level so that ...
as Mr aries said the toilet level should be at least 12mm down by floor level of bedroom or hall it should not be above bedroom level proper sunked to be provided on slab itself while designing the slab , sunken should be treated by waterproof course up to 1 feet above the floor level so that ...